The AI power trade: who really gets paid when data centers need electricity?
- Every AI data center needs power before it needs a single chip, and that has turned GE Vernova, Constellation and Vistra into AI stocks. In the November sell-off they fell with the chips: Vistra and GE Vernova about 20%, Constellation 6%.
- They are not the same bet. GE Vernova is paid upfront by customers queuing for turbines; Constellation sells power under 20-year contracts that mostly start in 2028 to 2032; Vistra earns market prices in Texas, where data-center politics just got harder.
- The best risk-reward today is in the companies whose cash does not depend on next year's power price. The highest risk sits with merchant generators that need both AI demand and Texas politics to cooperate.
The last time power stocks were this exciting was 2000. Calpine, Mirant and Dynegy rode the California electricity crisis to record highs on the idea that demand would outrun supply forever. Within five years Mirant and Calpine were in bankruptcy court. Twenty-six years later Calpine belongs to Constellation, and the same idea is back with a new driver: artificial intelligence.
The demand is real. PJM, the grid that serves the data-center belt from Virginia to Ohio, and ERCOT in Texas both set all-time peak-load records this summer, about 168 GW and 91 GW. The question for investors is not whether America needs more electricity. It is which companies turn that need into cash, and on what terms.
The scoreboard
| Company | What it sells | Price (Nov 25) | Since Oct 27 | Market cap | Forward P/E | Key number |
|---|---|---|---|---|---|---|
| GE Vernova | Turbines, grid equipment | $715.56 | −20% | $189B | ~29 | Backlog $197B; 2026 FCF guide $16–17B |
| Constellation | Nuclear + gas (Calpine) | $244.00 | −6% | $83B | ~19* | 2026 EPS guide $12.50–12.80 |
| Vistra | Texas & PJM generator | $119.60 | −18% | $41B | ~12 | 2027 EBITDA guide $7.7–8.5B |
| Eaton | Electrical equipment | $317.70 | −17% | $123B | ~20 | Data-center power gear |
| Vertiv | Cooling and power for data centers | $172.00 | −18% | $67B | ~19 | Pure data-center supplier |
| NextEra | Regulated utility + renewables | $84.50 | +3% | $179B | ~22 | Rose while AI names fell |
Prices and market caps from our database; forward P/E on consensus estimates. *Constellation on the midpoint of its own 2026 guidance. Since Oct 27 = price change to the Nov 25 close.
GE Vernova: the toll booth everyone has to pass
You cannot build a gas plant without a turbine, and three companies make large gas turbines. GE Vernova is the biggest. Its third quarter showed what scarcity looks like on paper: orders of $29.3 billion, up 96%, a backlog of $197 billion, and gas equipment under contract or reserved rising from 116 to 122 GW, heading for at least 130 GW by year-end. It now expects $16 to $17 billion of free cash flow in 2026, up from $11.5 to $12.5 billion three months ago.
Read that cash flow carefully. In the third quarter, $5.3 billion of it came from working capital, mostly customer down payments and fees to reserve production slots. That is the best kind of cash a manufacturer can get: customers pay before delivery because they fear being left without equipment. But it is also borrowed from the future. When those turbines ship in 2028 and 2029, the cash has already been spent, and the reported free cash flow will drop even if the business is healthy. On normal cash generation the stock is far from cheap at about 29 times forward earnings.
The risk for GE Vernova is the classic one for equipment makers: the order book looks endless at the top. If AI spending slows and some data-center projects are cancelled, reservations are the first thing customers walk away from.
Constellation: the contract is the product
Constellation owns the largest nuclear fleet in the country and, since January, Calpine's gas plants. Its third quarter was excellent: adjusted earnings of $5.06 a share against $3.04 a year ago, and full-year guidance raised for the second time to $12.50 to $12.80. More important are the contracts. About 8,500 MW of long-term deals have been signed this year, including a 20-year, 690 MW agreement with Amazon and a collaboration with Google on new nuclear capacity. Contracted output now covers about 45% of its clean baseload fleet.
The catch is timing. Most of the new contracts start paying between 2028 and 2032, and management has warned that the extra trading margins of 2026 will be smaller in 2027. At about 19 times this year's earnings, the market is paying today for income that arrives in three to six years. That is reasonable for 20-year contracts with the strongest companies in the world, but it leaves little room if 2027 earnings stall.
Vistra: the purest bet on power prices
Vistra had a record quarter: adjusted EBITDA up more than 50% to $2.38 billion, and 2027 guidance of $7.7 to $8.5 billion, including the Cogentrix plants and a nuclear power agreement with Meta at the Perry plant. Management targets about $14 of free cash flow per share in 2027, which puts the stock at under nine times that figure.
Why so cheap, then? Because Vistra sells much of its power at market prices in Texas, and Texas has become the risk. Forward power prices there have fallen, a new governor brings talk of a data-center moratorium, and an ERCOT audit and a permit pause have slowed new connections. Vistra also carries about $18 billion of debt, so falling prices hit its equity harder. It is the cheapest of the three because it is the one most exposed to things it cannot control.
What the market is telling us
The most revealing number in the scoreboard is the last row. While the AI-linked power names fell 6% to 20%, NextEra, Duke and Southern, the regulated utilities, rose. Investors did not sell electricity; they sold the part of electricity that is priced as an AI story. That is the same lesson as in the chip sector: the closer a company's earnings are to AI capex budgets, the harder it falls when those budgets are questioned.
Three scenarios
- Steady build-out (about 50%): data centers keep connecting, slower in Texas, faster in PJM. GE Vernova's backlog converts at higher prices, Constellation's contracts start on schedule, Vistra's 2027 guidance holds. The group recovers part of its November losses.
- AI capex digestion (about 30%): hyperscalers cut 2027 spending growth, some projects are delayed, turbine reservations are cancelled or pushed out. GE Vernova and Vistra take the biggest hits; Constellation's contracts protect it.
- Power shortage (about 20%): demand outruns new supply, capacity prices spike again. Vistra gains most, followed by Constellation; regulators step in with price caps, which is the risk inside the bull case.
Bottom line
The AI power trade is not one trade. If you want exposure with the least dependence on next year's power price, Constellation's contracts are the most defensible, at a full price. GE Vernova is the best business of the three but its cash flow is flattered by prepayments, so we would wait for a better entry. Vistra is the cheapest and the most leveraged to both upside and policy risk: a position to size small. And as in 2000, the companies that look safest at the top of a power boom are the ones that sold their output under contract before the boom ended. For the wider picture, read Is AI a bubble?, and run your own numbers in the DCF calculator.
Frequently asked questions
What are the best AI power stocks?
The main listed names are GE Vernova (gas turbines and grid equipment), Constellation Energy (nuclear and gas with long-term contracts) and Vistra (power generation in Texas and PJM). They carry very different risks; Constellation is the most contracted, Vistra the most exposed to market power prices.
Why did Vistra stock fall?
It fell about 18% from late October with the wider AI sell-off, and because Texas, its main market, faces lower forward power prices and new political uncertainty over data-center connections.
Is GE Vernova overvalued?
At about 29 times forward earnings it is expensive. Its 2026 free cash flow of $16 to $17 billion is boosted by customer down payments that will reverse as turbines are delivered.
When do Constellation’s data-center contracts start?
Most of the new long-term contracts start between 2028 and 2032, so they support earnings later in the decade rather than in 2027.
Sources: company third-quarter 2026 results releases (GE Vernova Oct 28, Vistra Nov 6, Constellation Nov 9); prices from our database. Analysis for education, not investment advice.